Bilby Plc

Completed Projects - Construction and Major Refurbishments

Client: Golding Homes

Location: The Limes, Ashford, Kent

Scope: Major finishing works to a new build development of eight, self-contained one bedroom flats / maisonettes and support facilities. We took this project over from a previous contractor.

Duration: March 2016 to January 2017

Client: MCCH

Location: Former Archbishop Courtenay School, Maidstone, Kent

Scope: Re-development of the former Archbishop Courtenay School in Maidstone, creating 7 residential units and a training flat to provide transitional living and training for young adults with learning difficulties.

Duration: March 2015 to June 2016

Client: MOAT Housing

Location: James Watt Way, Erith, Kent

Scope: Major completion works to a 5 storey, timber frame block of 40 apartments, built for affordable rent. We took this project over from a previous contractor. The building suffered a fire in August 2016 and we are working with the client to undertake the reinstatement.

Duration: April 2015 to June 2016

Client: Golding Homes

Location: Tovil Community Centre, Maidstone, Kent

Scope: Construction of a new two-storey community centre built for the Maidstone YMCA. Internally the centre featured a main hall area, kitchen and WCs and externally a games court.

Duration: March 2015 to January 2016

Client: Golding Homes

Location: Harrietsham, Maidstone, Kent

Scope: Major completion works to 10 new town houses across two separate blocks. We took the project over from a previous contractor.

Duration: September 2014 to September 2015

Client: Tonbridge Grammar School

Location: Tonbridge, Kent

Scope: Major remodelling and refurbishment works to the music / arts block and sixth form block.

Duration: May 2015 to September 2015

Client: AmicusHorizon

Location: Bale Grove, Sittingbourne, Kent

Scope: New build development of 14 new homes for shared ownership.

Duration: March 2014 to April 2015

Client: Ashford Borough Council

Location: Various sites across Ashford, Kent

Scope: New build developments across 5 sites comprising 17 houses, 4 apartments and 4 bungalows, built for affordable rent.The sites were a mixture of former garage and greenfield areas. Some of the properties were built with disabled adaptations.

Duration: March 2014 to March 2015

Client: Eldon Housing Association

Location: 30A Russell Hill, Croydon

Scope: Construction of timber frame building comprising 11 one / two bedroom apartments, designed for the over 55s.

Duration: September 2012 to April 2014